Taiwan | 2010-2014

The Multifunctional Uses of ACEBag™ for Dredged Soil Containment and Cofferdam Construction, Nantou, Taiwan

Products:ACEBag™

Application: Sediment Dredging, Levees and Dikes

Background

Wushe Reservoir, also known as Wanda Reservoir, is a curved concrete gravity dam at the upstream of Jhuoshuei River in central Taiwan. The construction of the dam started in 1939, but was interrupted by the Pacific War, and finally it was completed in 1957. Wushe Reservoir is 114 m high and 205 m long. The total volume is around 249,000 m3. It performs both functions of water reservoir and hydroelectric power. However, these functions were compromised due to sedimentation like most reservoirs in Taiwan. Because Taiwan is located in one of the main paths of North Western Pacific typhoons, approximately three to four typhoons attack the island each year. Heavy rainfall from the typhoons usually brings down large amount of soil from the mountain and subsequently deposit in the reservoirs.

Problem / Task

In 2009, one devastating storm, Typhoon Morakot, attacked Taiwan and caused catastrophic damage to the island. The amount of its 24-hour rainfall was record-breaking high at 3060mm (1). It’s estimated that about 60 million m3 of silt was brought into the reservoirs and rivers in central and southern Taiwan by that single storm. In early 2011, the amount of silt in Wushe Reservoir had exceeded 80 million m3. The sedimentation made half of the reservoir dried up and the riverbed of its inflow river, the Tarot Bay River, aggraded. Consequently, the water storage capacity of the reservoir was reduced by 60%, and could not retain enough water for the need of local residents and farmers. Therefore, it was imperative to dredge the reservoir. Since the dredging work was in the reservoir watershed, any contamination to the water resource should be properly controlled. Hence, it was critical to tackle the dredged materials carefully.

Solution/ Design & Construction

In order to remove the large amount of sediment in the reservoir efficiently, a vast temporary sediment deposit area for the dredged material was planned to set adjacent to the Tarot Bay River. Then, a cofferdam was to be built for stabilizing the area and preventing riverbank clods from falling into the river. Considering the need of environmental protection, limited budget, and short construction time, gabions (ACEGabion™) loaded with geotextile bags (ACEBag™) were thought as the best choice for constructing the cofferdam. With appropriate porosity and excellent permeability, ACEBag™ can contain and dewater the sludge obtained from the dredging. At the same time, the filled geotextile bags can replace gravels to be gabion filler. When comparing the methods of using gravel gabion fillers and in-situ sediment gabion fillers, the latter saved more time and money, since it notably reduced the resources allocated for sediment removing and gravel filling. Besides, the carbon emission caused by material transportation was significantly reduced. Furthermore, gabion with ACEBag™ is easier to be removed after the project completion.

Result

During construction, the cofferdam consisted of gabions and ACEBag™ geotextile bags ensured the stability of the temporary sediment deposit area and facilitated the dredging job. ACEBag™ makes the usage of waste materials possible and brings about great benefits in the dredging project. Now, the reservoir is able to store more water and operate efficiently. The local residents and farmers are no longer short in water supply.

Sediment Dredging

Sediment Dredging

Freshwater and seawater currents carry sediments into harbors and other naval passageways constricting navigation and the flow of water. Dredging the sediment a...

Levees and Dikes

Levees and Dikes

Levees or Dikes are applied to protect the safety of people and surroundings against flooding. Stacked ACETube® geotextile tubes or wrapped ACEGrid® geogrid rei...

Related Products

Similar Case Studies

Detention Pond under the  Shalu Overpass of Freeway No. 3, Taichung, Taiwan

Detention Pond under the Shalu Overpass of Freeway No. 3, Taichung, Taiwan

Taiwan | 2015-2019
Products:ACEGrid® GG, ACETex® NW, ACESandbag™ EC, ACEPin™ T, ACEDrain™ S
Application:Flood Detention
Geosynthetic Detention Basin at Shalu Interchange, Taiwan

Geosynthetic Detention Basin at Shalu Interchange, Taiwan

Taiwan | 2015-2019
Products:ACEGrid® GG, ACETex® NW, ACESandbag™ EC, ACEPin™ T, ACEDrain™ S, ACELiner™
Application:Flood Detention
Dredge and Land Reclamation, Anping Harbor, Tainan, Taiwan

Dredge and Land Reclamation, Anping Harbor, Tainan, Taiwan

Taiwan | 2015-2019
Products:ACETube® - hydraulic structures
Application:Sediment Dredging, Seawalls and Bulkheads